NLI engineering continues work on GoliatPublished 10.01.11 The contract for NLI Engineering will consist of complete engineering of two skids. One skid of 5 hydrocyclones, a total of approx. 80 tons, and another skid of 2. EPCON - tanks CFU (Compact FLOATATION Unit) which will weigh about 35 tons. The delivery from NLI Engineering will be a complete fabrication base for the fabrication of the plant. The project is already well underway and new staffing is continuously under demand. In the most hectic phase of engineering, there will be more than 20 people involved, both at the office at Vear and at Kjeller in Norway. "We are very pleased that MI EPCON wish to continue further cooperation with NLI. We choose to believe that this is due to a very successful implementation and delivery of the previous project, a EPCON CFU skid to the BP Valhall ", says project manager at NLI Engineering, Terje Ulseth. The plants to MI EPCON based on the technology EPCON CFU - Compact FLOATATION Unit - which is among the world leading for the treatment of produced water. NLI Engineering has been involved in the Goliat project since it's early beginning with Eni Norway and Sevan Marine. |
|
|||||
|
||||||||